Advantages: Looking for information about this vessel. Any thoughts on this vessel? Was the pay decent?
Disadvantages: No personal experience yet, just gathering info.
The 'Hallaig', serving on the route Sconser-Raasay, suffered a technical issue with the aft drive cooling system, on the morning of Nov 10. As a consequence, the service had to be suspended to address...
The 'Hallaig', serving on the route Sconser-Raasay, suffered a defect with its forward steering system on Nov 2, which reduced the vessel's operational capabilities. Due to a forecast of strong winds...
The 'Hallaig', serving on the route Sconser - Raasay, suffered a technical issue affecting the Voith unit on Oct 12. As a consequence, the Vessel was unavailable for service on Oct 13. Spares have bee...
The 'Hallaig', serving on the route Sconser-Raasay, suffered a technical issue with the vessel's generator on Aug 24. As a consequence. the service was suspended timewise. After repairs in Raasay, the...
Due to a technical issue on the 'Hallaig', serving on the route Sconser-Raasay, on July 17, the scheduled 07:55 a.m. sailing departing from Raasay and the 08:25 a.m. sailing departing from Sconser had...
Pending attendance of shore-based engineers, weather restrictions have been placed on the 'Hallaig', serving on the route Raasay-Sconser, on Feb 2, 2025.In order to provide additional capacity, the 'H...
The 'Hallaig', which had suffered a battery failure and was taken out of service in Raasay on Sep 7, 2023, has been forced to run exclusively on diesel fuel for some time and will continue to do so we...